You have been building the D35 for 50 years, an audit of the Ministry of Transport has reproached. To be finished in 2029
The construction of the D35 motorway between Hradec Králové and Olomouc has been underway since the 1970s and is still not finished, the Supreme Audit Office (SAO) has reproached the Ministry of Transport. It has been hampered by incomplete documents from the state and objections from the participants in the proceedings. “We are trying to speed up preparations,” the ministry responded. Although the D35 motorway between Hradec Králové and Olomouc is one of the most important parts of the motorway network, its construction is delayed and expensive. Although construction began in the 1970s, the Road and Motorway Directorate (ŘSD) expects it to be fully operational by 2030. The total construction time of the 210-kilometre-long motorway will therefore exceed 50 years.